Validation
preparation of (DQ/)IQ/OQ(/PQ) protocols and reports
(including discussion, check and approval by client's QA)
- hardware layout and software design (DQ) (FAT)
- documentation (IQ) (FAT and SAT)
- automation hardware (IQ) (FAT and SAT)
- operating platform and software installation (PLC,PCS,SCADA,OP,...) (IQ) (FAT and SAT)
- electrical hardware of cabinets (IQ) (FAT and SAT)
- electrical wiring and pneumatic hosing (IQ) (SAT)
- measurement and control equipment (IQ) (SAT)
- safety relevant components and operations (OQ) (FAT and SAT)
- calibration of measurement and control equipment (OQ) (FAT and SAT)
- signal- and line test (I/O level run-off and SCADA) (OQ) (FAT and SAT)
- alarms and controls (sequence level run-off and SCADA) (OQ) (FAT and SAT)
- custom built add-ons (sequence level run off and SCADA) (OQ) (FAT and SAT)
- supplementary visualisation (operating panels) (OQ) (FAT and SAT)
- safety relevant issues (alarm system) (OQ) (FAT and SAT)
- unit operations (operation level run-off and SCADA) (OQ) (FAT and SAT)
- batch and recipe management (operation level run off and SCADA/PCS) (OQ) (FAT and SAT)
- automation system performance (PQ) (security, load, networks, time base, Y2K) (FAT and SAT)
- automation system maintenance (PQ) (back up, restore, restart) (FAT and SAT)
- change request and error magement
preparation of operator manual (English, German, French, Turkish)
- automation and operation issues (visualisation, security...) and manual devices
- security instructions
- draft SOPs technological run-off control (technological unit operations with manual interventions)
- draft SOP preventive maintenance
- draft SOP trouble shooting and failure elimination
- draft SOP shutdown and startup of installation
- draft SOP calibration
- draft SOP for backup, restore and restart (see above)
SAT Automation Software at client's site (SAT - Site Acceptance Test)
- SAT of PLC/PCS, SCADA, OPs:
- documented check of software design (DQ)
- documented check of documentation (IQ)
- documented check of operating platform and software installation (PLC,PCS,SCADA,OP,...) (IQ)
- documented check of signal- and line test (I/O level run-off and SCADA) (OQ)
- documented check of alarms and control (sequence level run-off and SCADA) (OQ)
- documented check of custom built add-ons (sequence level run-off and SCADA) (OQ)
- documented check of supplementary visualisation (operating panels) (OQ)
- documented check of operation of safety relevant issues (alarm system) (OQ)
- documented check of unit operations (operation level run off and SCADA) (OQ)
- documented check of batch and recipe management (operation level run-off and SCADA) (OQ)
- documented check of automation system performance (PQ)
- documented check of automation system maintenance (PQ)
retrospective validation
- study of installation
- risk assessment
- preparation of missing design documents
- preparation of experience report
preparation of validation protocol and reports
- execution of validation
- preparation of final documentation
- assembly of design, as built, validation according to GaMP guidelines and component documentation
- preparation of overall spare parts list